Land To The South Of, Wittering Ford Road, Stamford,, Cambridgeshire, PE9 3HX
Wittering Ford Road is a 3 MW battery storage project in Eastern. The applicant or operator on record is Solar Charging (Lark Energy). Planning permission has been granted as of November 2019 and it is awaiting construction. The determining authority is Peterborough, reference 19β¦
Consented / Approved
Project stageConsented
PlanningSep 2019 (completed)
ConsentedNov 2019 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2019-12-20.
Registered planning capacity; not measured generation.
Wittering Ford Road is a 3 MW battery storage project in Eastern. The applicant or operator on record is Solar Charging (Lark Energy). Planning permission has been granted as of November 2019 and it is awaiting construction. The determining authority is Peterborough, reference 19/01261/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
3.000 MW
Battery chemistry
Co-located with RE
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Solar Charging (Lark Energy)
Owner / operator
Solar Charging (Lark Energy)
Year consented
2019
Location
Land To The South Of, Wittering Ford Road, Stamford,, Cambridgeshire, PE9 3HX