Winterton Road - Battery Energy Storage is a 95 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Newton Energi Limited. Planning permission has been granted as of December 2022 and it is awaiting construction. The determining authority is…

Consented / Approved
Project stageConsented
  1. PlanningAug 2021 (completed)
  2. ConsentedDec 2022 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2021-09-15.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

95.000 MW
Power Capacity

πŸ“‹ Project Overview

Winterton Road - Battery Energy Storage is a 95 MW battery storage project in Yorkshire and Humber. The applicant or operator on record is Newton Energi Limited. Planning permission has been granted as of December 2022 and it is awaiting construction. The determining authority is North Lincolnshire, reference PA/2021/1291.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)95.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNewton Energi Limited
Owner / operatorNewton Energi Limited
Year consented2022
LocationN/O Gala Bingo, Winterton Road, Scunthorpe, Lincolnshire, DN15 0DH
RegionYorkshire and Humber
Coordinates53.5971918Β°N, 0.6412304Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2021-08-12
2022-12-16