Land North East And North West Of Farmhouse Braidlie (Windy Edge) Hawick, Borders
Windy Edge Wind Farm is a 27 MW onshore wind project in Scotland. The applicant or operator on record is Energiekontor. The planning permission has expired. The determining authority is Scottish Borders, reference 13/00789/FUL.β¦
Expired
Project stageConsent lapsed
PlanningJul 2013 (completed)
ConsentedJun 2016 (completed)
Consent lapsed (project stopped here)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Expired.
Official register: July 2026
Recorded status: Planning Permission Expired. Source record updated 2018-10-29.
Registered planning capacity; not measured generation.
Windy Edge Wind Farm is a 27 MW onshore wind project in Scotland. The applicant or operator on record is Energiekontor. The planning permission has expired. The determining authority is Scottish Borders, reference 13/00789/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
27.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Energiekontor
Owner / operator
Energiekontor
Year consented
2016
Location