πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Willows power and recycling centre (EfW)

Land at The Willows Business Park, High (Saddlebow) Road, Saddlebow Industrial Area, King's Lynn, Norfolk, PE34 3RD

Willows power and recycling centre (EfW) is a 24.2 MW bioenergy / waste project in Eastern. The applicant or operator on record is Cory Environmental. The application has been withdrawn or the scheme abandoned. The determining authority is King's Lynn and West Norfolk, reference …

Withdrawn
Project stageWithdrawn / abandoned
  1. PlanningJun 2011 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Abandoned.

Official register: July 2026

Recorded status: Abandoned. Source record updated 2015-02-18.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

24.200 MW
Registered Capacity

πŸ“‹ Project Overview

Willows power and recycling centre (EfW) is a 24.2 MW bioenergy / waste project in Eastern. The applicant or operator on record is Cory Environmental. The application has been withdrawn or the scheme abandoned. The determining authority is King's Lynn and West Norfolk, reference C/2/2011/2020.

πŸ”§ Technical Specifications

Capacity (MW)24.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperCory Environmental
Owner / operatorCory Environmental
LocationLand at The Willows Business Park, High (Saddlebow) Road, Saddlebow Industrial Area, King's Lynn, Norfolk, PE34 3RD
RegionEastern
Coordinates52.7284753Β°N, 0.3843324Β°E

Additional published register fields

Registered technologyEfW Incineration

πŸ“… Project Timeline

2011-06-10