On Land at, Whitley Wood Farm, Whitley Lane, Ashcott, Bridgwater, Somerset

Whitley Farm (1 of 2) is a 3.5 MW solar farm project in South West. The applicant or operator on record is NextEnery Solar Fund (NESF). It is recorded as operational since March 2014. The determining authority is Somerset, reference 01/13/00015.…

Operational Β· Since 2014
Project stageOperating
  1. PlanningJul 2013 (completed)
  2. ConsentedOct 2013 (completed)
  3. Construction (completed)
  4. OperatingMar 2014 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2018-07-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

3.500 MW
Registered Capacity
2014
Commissioned

πŸ“‹ Project Overview

Whitley Farm (1 of 2) is a 3.5 MW solar farm project in South West. The applicant or operator on record is NextEnery Solar Fund (NESF). It is recorded as operational since March 2014. The determining authority is Somerset, reference 01/13/00015.

Site Schematic

SUBSTATION ? ha Β· 3.5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)3.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperNextEnery Solar Fund (NESF)
Owner / operatorNextEnery Solar Fund (NESF)
Year consented2013
Commissioned / target2014
LocationOn Land at, Whitley Wood Farm, Whitley Lane, Ashcott, Bridgwater, Somerset
RegionSouth West
Coordinates51.1302981Β°N, 2.7952542Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID11004
Mounting Type for SolarGround

πŸ“… Project Timeline

2013-07-17
2013-10-15
2014-03-31