Eaglesham Moor, to the south of Glasgow, Strathclyde
Whitelee Windfarm Extension Phase 1 is a 108 MW onshore wind project in Scotland. The applicant or operator on record is Scottish Power Renewables. It is recorded as operational since October 2012. The determining authority is Scottish Government (S36).β¦
OperationalΒ· Since 2012
Project stageOperating
PlanningApr 2008 (completed)
ConsentedMay 2009 (completed)
ConstructionDec 2010 (completed)
OperatingOct 2012 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2013-04-22.
Registered planning capacity; not measured generation.
Whitelee Windfarm Extension Phase 1 is a 108 MW onshore wind project in Scotland. The applicant or operator on record is Scottish Power Renewables. It is recorded as operational since October 2012. The determining authority is Scottish Government (S36).
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
108.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Scottish Power Renewables
Owner / operator
Scottish Power Renewables
Year consented
2009
Construction started
2010
Commissioned / target
2012
Location
Eaglesham Moor, to the south of Glasgow, Strathclyde