Land off Weycock Cross, Waycock Road, Barry, South Glamorgan, South Glamorgan, CF62 3AA

Weycock Road is a 7 MW solar farm project in Wales. The applicant or operator on record is Elgin Energy EsCo. It is recorded as operational since March 2016. The determining authority is Vale of Glamorgan, reference 2014/00081/FUL.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningJan 2014 (completed)
  2. ConsentedAug 2014 (completed)
  3. ConstructionNov 2015 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-06-21.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

7.000 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Weycock Road is a 7 MW solar farm project in Wales. The applicant or operator on record is Elgin Energy EsCo. It is recorded as operational since March 2016. The determining authority is Vale of Glamorgan, reference 2014/00081/FUL.

Site Schematic

SUBSTATION ? ha Β· 7 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)7.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperElgin Energy EsCo
Owner / operatorElgin Energy EsCo
Year consented2014
Construction started2015
Commissioned / target2016
LocationLand off Weycock Cross, Waycock Road, Barry, South Glamorgan, South Glamorgan, CF62 3AA
RegionWales
Coordinates51.4177978Β°N, 3.3075337Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)179017

πŸ“… Project Timeline

2014-01-22
2014-08-01
2015-11-26
2016-03-02