Solar Farm

Westfield Solar Farm & Battery

Westfield O C C S, Fife, KY5 0UG

Westfield Solar Farm & Battery is a 30 MW solar farm project in Scotland. The applicant or operator on record is Brockwell Energy Limited. Planning permission has been granted as of February 2021 and it is awaiting construction. The determining authority is Fife, reference 20/022…

Consented / Approved
Project stageConsented
  1. PlanningSep 2020 (completed)
  2. ConsentedFeb 2021 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-03-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

30.000 MW
Registered Capacity

πŸ“‹ Project Overview

Westfield Solar Farm & Battery is a 30 MW solar farm project in Scotland. The applicant or operator on record is Brockwell Energy Limited. Planning permission has been granted as of February 2021 and it is awaiting construction. The determining authority is Fife, reference 20/02221/ARC.

Site Schematic

SUBSTATION ? ha Β· 30 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)30.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBrockwell Energy Limited
Owner / operatorBrockwell Energy Limited
Year consented2021
LocationWestfield O C C S, Fife, KY5 0UG
RegionScotland
Coordinates56.1785557Β°N, 3.2882697Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID20392
CfD Allocation RoundAR7a
CfD Capacity (MW)29.9
Mounting Type for SolarGround
Solar Site Area (sqm)350000

πŸ“… Project Timeline

2020-09-30
2021-02-12