25 km north of Spurn Head at the River Humber estuary., Offshore
Westermost Rough A is a 210 MW offshore wind project in Offshore. The applicant or operator on record is Orsted (formerly Dong Energy). It is recorded as operational since May 2015. The determining authority is DECC (S36).β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningNov 2009 (completed)
ConsentedNov 2011 (completed)
ConstructionFeb 2014 (completed)
OperatingMay 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2018-04-05.
Registered planning capacity; not measured generation.
Westermost Rough A is a 210 MW offshore wind project in Offshore. The applicant or operator on record is Orsted (formerly Dong Energy). It is recorded as operational since May 2015. The determining authority is DECC (S36).
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
210.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Orsted (formerly Dong Energy)
Owner / operator
Orsted (formerly Dong Energy)
Year consented
2011
Construction started
2014
Commissioned / target
2015
Location
25 km north of Spurn Head at the River Humber estuary., Offshore