Land Between Fawkham Road And Crowhurst Lane West Kingsdown KENT (Intersecting By M20), Kent
West Kingdown is a 20 MW solar farm project in South East. The applicant or operator on record is Hive Energy. The application has been withdrawn or the scheme abandoned. The determining authority is Sevenoaks, reference 13/02487/FUL.β¦
Withdrawn
Project stageWithdrawn / abandoned
PlanningAug 2013 (completed)
Withdrawn / abandoned (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Application Withdrawn.
Official register: July 2026
Recorded status: Planning Application Withdrawn. Source record updated 2014-01-24.
Registered planning capacity; not measured generation.
West Kingdown is a 20 MW solar farm project in South East. The applicant or operator on record is Hive Energy. The application has been withdrawn or the scheme abandoned. The determining authority is Sevenoaks, reference 13/02487/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
20.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Hive Energy
Owner / operator
Hive Energy
Location
Land Between Fawkham Road And Crowhurst Lane West Kingsdown KENT (Intersecting By M20), Kent