West Buckland School, West Buckland, Barnstaple, Devon, EX32 0SX
West Buckland School, West Buckland - Solar Panels is a 0.41 MW solar farm project in South West. The applicant or operator on record is West Buckland School. Planning permission has been granted as of June 2023 and it is awaiting construction. The determining authority is North β¦
Consented / Approved
Project stageConsented
PlanningFeb 2023 (completed)
ConsentedJun 2023 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2023-06-19.
Registered planning capacity; not measured generation.
West Buckland School, West Buckland - Solar Panels is a 0.41 MW solar farm project in South West. The applicant or operator on record is West Buckland School. Planning permission has been granted as of June 2023 and it is awaiting construction. The determining authority is North Devon, reference 76294.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.410 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
West Buckland School
Owner / operator
West Buckland School
Year consented
2023
Location