East of the West Boldon Substation, 400 metres south of the A184 and 300m East of the A189 in South Tyneside, Tyne And Wear, NE35 9PE
West Boldon Substation - Battery Energy Storage is a 60 MW battery storage project in North East. The applicant or operator on record is Whirlwind Energy Storage Limited. Planning permission has been granted as of December 2024 and it is awaiting construction. The determining autβ¦
Consented / Approved
Project stageConsented
PlanningJul 2023 (completed)
ConsentedDec 2024 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Appeal Granted.
Official register: July 2026
Recorded status: Appeal Granted. Source record updated 2025-07-15.
Registered planning capacity; not measured generation.
West Boldon Substation - Battery Energy Storage is a 60 MW battery storage project in North East. The applicant or operator on record is Whirlwind Energy Storage Limited. Planning permission has been granted as of December 2024 and it is awaiting construction. The determining authority is South Tyneside, reference ST/0486/23/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
60.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Whirlwind Energy Storage Limited
Owner / operator
Whirlwind Energy Storage Limited
Year consented
2024
Location
East of the West Boldon Substation, 400 metres south of the A184 and 300m East of the A189 in South Tyneside, Tyne And Wear, NE35 9PE