Land West of Fernbury Farm, Tempsford Road, Everton, Bedfordshire, SG19 2JW
Waterloo solar park is a 14.6 MW solar farm project in Eastern. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since March 2015. The determining authority is Central Bedfordshire, reference CB/13/03549/FULL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningOct 2013 (completed)
ConsentedApr 2014 (completed)
ConstructionJan 2015 (completed)
OperatingMar 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-05-13.
Registered planning capacity; not measured generation.
Waterloo solar park is a 14.6 MW solar farm project in Eastern. The applicant or operator on record is Lightsource Renewable Energy. It is recorded as operational since March 2015. The determining authority is Central Bedfordshire, reference CB/13/03549/FULL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
14.600 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Lightsource Renewable Energy
Owner / operator
Lightsource Renewable Energy
Year consented
2014
Construction started
2015
Commissioned / target
2015
Location
Land West of Fernbury Farm, Tempsford Road, Everton, Bedfordshire, SG19 2JW