Washwood

Washwood Heath Energy Recovery Centre, West Midlands

Washwood is a 8 MW other registered technology project in West Midlands. The applicant or operator on record is Clean Power Properties & Network Rail Infrastructure. The scheme is currently in the planning system, submitted August 2012. The determining authority is Birmingham, re…

Revised
Project stageSuperseded by a new application
  1. PlanningAug 2012 (completed)
  2. Superseded by a new application (project stopped here)
  3. ConsentedNov 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2014-07-23.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

8.000 MW
Registered Capacity

πŸ“‹ Project Overview

Washwood is a 8 MW other registered technology project in West Midlands. The applicant or operator on record is Clean Power Properties & Network Rail Infrastructure. The scheme is currently in the planning system, submitted August 2012. The determining authority is Birmingham, reference 2012/05409/PA.

πŸ”§ Technical Specifications

Capacity (MW)8.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperClean Power Properties & Network Rail Infrastructure
Owner / operatorClean Power Properties & Network Rail Infrastructure
Year consented2012
LocationWashwood Heath Energy Recovery Centre, West Midlands
RegionWest Midlands
Coordinates52.5038502Β°N, 1.841174Β°W

Additional published register fields

Registered technologyAdvanced Conversion Technologies
Are they re-applying (New REPD Ref)5628

πŸ“… Project Timeline

2012-08-08
2012-11-23