Consented / Approved
Project stageConsented
  1. PlanningJul 2024 (completed)
  2. ConsentedOct 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-12-02.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Power Capacity

πŸ“‹ Project Overview

Ware Solar Park - Solar Farm & Battery Energy Storage is a 5 MW battery storage project in Eastern. The applicant or operator on record is The Farm Energy Company. Planning permission has been granted as of October 2025 and it is awaiting construction. The determining authority is East Hertfordshire, reference 3/24/1275/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperThe Farm Energy Company
Owner / operatorThe Farm Energy Company
Year consented2025
LocationWest Of Ware Ware Park Farm, Hertfordshire, SG12 0EB
RegionEastern
Coordinates51.8121511Β°N, 0.0597169Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2024-07-12