Opposite Walpole Sub Station Walpole Bank Walpole St Andrew, Cambridgeshire, PE14 7HZ
Walpole Sub Station, Walpole Bank - Battery Storage is a 100 MW battery storage project in Eastern. The applicant or operator on record is Henry Energy Limited. Planning permission has been granted as of July 2023 and it is awaiting construction. The determining authority is Kingβ¦
Consented / Approved
Project stageConsented
PlanningNov 2022 (completed)
ConsentedJul 2023 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2026-02-24.
Registered planning capacity; not measured generation.
Walpole Sub Station, Walpole Bank - Battery Storage is a 100 MW battery storage project in Eastern. The applicant or operator on record is Henry Energy Limited. Planning permission has been granted as of July 2023 and it is awaiting construction. The determining authority is King's Lynn and West Norfolk, reference 22/02021/F.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
100.000 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Henry Energy Limited
Owner / operator
Henry Energy Limited
Year consented
2023
Location
Opposite Walpole Sub Station Walpole Bank Walpole St Andrew, Cambridgeshire, PE14 7HZ