Manor Farm St Michaels Road Verwood Dorset, Dorset, BH31 6JA
Verwood Solar Farm is a 20.4 MW solar farm project in South West. The applicant or operator on record is Foresight. It is recorded as operational since February 2015. The determining authority is Dorset, reference 3/14/0457/FUL.β¦
OperationalΒ· Since 2015
Project stageOperating
PlanningApr 2014 (completed)
ConsentedJul 2014 (completed)
ConstructionNov 2014 (completed)
OperatingFeb 2015 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2015-05-28.
Registered planning capacity; not measured generation.
Verwood Solar Farm is a 20.4 MW solar farm project in South West. The applicant or operator on record is Foresight. It is recorded as operational since February 2015. The determining authority is Dorset, reference 3/14/0457/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
20.400 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Foresight
Owner / operator
Foresight
Year consented
2014
Construction started
2014
Commissioned / target
2015
Location