Building 1, Vantage Point Business Village Mitcheldean, Gloucestershire, GL17 0DD
Vantage Point is a 1.4 MW solar farm project in South West. The applicant or operator on record is Bee Green Solar. It is recorded as operational since September 2011. The determining authority is Forest of Dean, reference P0825/11/FUL.β¦
OperationalΒ· Since 2011
Project stageOperating
PlanningMay 2011 (completed)
ConsentedJun 2011 (completed)
ConstructionJul 2011 (completed)
OperatingSep 2011 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-03-14.
Registered planning capacity; not measured generation.
Vantage Point is a 1.4 MW solar farm project in South West. The applicant or operator on record is Bee Green Solar. It is recorded as operational since September 2011. The determining authority is Forest of Dean, reference P0825/11/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
1.400 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Bee Green Solar
Owner / operator
Bee Green Solar
Year consented
2011
Construction started
2011
Commissioned / target
2011
Location
Building 1, Vantage Point Business Village Mitcheldean, Gloucestershire, GL17 0DD