Upper Newton Farm (Blythe House) - Solar Farm & Battery Storage is a 27.7 MW solar farm project in West Midlands. The applicant or operator on record is Innova Renewables. Planning permission has been granted as of February 2023 and it is awaiting construction. The determining au…

Consented / Approved
Project stageConsented
  1. PlanningMar 2022 (completed)
  2. ConsentedFeb 2023 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2026-05-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

27.700 MW
Registered Capacity

πŸ“‹ Project Overview

Upper Newton Farm (Blythe House) - Solar Farm & Battery Storage is a 27.7 MW solar farm project in West Midlands. The applicant or operator on record is Innova Renewables. Planning permission has been granted as of February 2023 and it is awaiting construction. The determining authority is Staffordshire Moorlands, reference SMD/2022/0160.

Site Schematic

SUBSTATION ? ha Β· 27.7 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)27.700 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperInnova Renewables
Owner / operatorInnova Renewables
Year consented2023
LocationUpper Newton Farm, Draycott Road, Upper Tean, Staffordshire, ST10 4JN
RegionWest Midlands
Coordinates52.9473298Β°N, 2.0203324Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID10977
CfD Allocation RoundAR7a
CfD Capacity (MW)45.3
Mounting Type for SolarGround
Solar Site Area (sqm)421800

πŸ“… Project Timeline

2022-03-24
2023-02-01