Unipres Uk Ltd, Cherry Blossom Way, Washington, Sunderland, Tyne and Wear, Tyne and Wear, SR5 3NT
Unipres building is a 4.9 MW solar farm project in North East. The applicant or operator on record is Regenerco. It is recorded as operational since July 2020. The determining authority is Sunderland, reference 18/02055/FUL.β¦
OperationalΒ· Since 2020
Project stageOperating
PlanningDec 2018 (completed)
ConsentedFeb 2019 (completed)
ConstructionFeb 2020 (completed)
OperatingJul 2020 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2023-03-28.
Registered planning capacity; not measured generation.
Unipres building is a 4.9 MW solar farm project in North East. The applicant or operator on record is Regenerco. It is recorded as operational since July 2020. The determining authority is Sunderland, reference 18/02055/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
4.900 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Regenerco
Owner / operator
Regenerco
Year consented
2019
Construction started
2020
Commissioned / target
2020
Location
Unipres Uk Ltd, Cherry Blossom Way, Washington, Sunderland, Tyne and Wear, Tyne and Wear, SR5 3NT