Ulnes Walton Energy is a 1.3 MW bioenergy / waste project in North West. The applicant or operator on record is SITA UK. It is recorded as operational since March 2003. The determining authority is Chorley, reference 09/00/0050.…

Operational Β· Since 2003
Project stageOperating
  1. PlanningJan 2000 (completed)
  2. ConsentedMay 2000 (completed)
  3. Construction (completed)
  4. OperatingMar 2003 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2006-05-24.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.300 MW
Registered Capacity
2003
Commissioned

πŸ“‹ Project Overview

Ulnes Walton Energy is a 1.3 MW bioenergy / waste project in North West. The applicant or operator on record is SITA UK. It is recorded as operational since March 2003. The determining authority is Chorley, reference 09/00/0050.

πŸ”§ Technical Specifications

Capacity (MW)1.300 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSITA UK
Owner / operatorSITA UK
Year consented2000
Commissioned / target2003
LocationRidley Lane, Croston, Preston, Lancashire, Lancashire
RegionNorth West
Coordinates53.6767031Β°N, 2.7674725Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

2000-01-20
2000-05-10
2003-03-03