πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Tythegston Landfill Site

Tythegston Landfill Site Tythegston Mid Glamorgan, Mid Glamorgan

Tythegston Landfill Site is a 1.2 MW bioenergy / waste project in Wales. The applicant or operator on record is Renewable Power Generation Ltd. It is recorded as operational since October 1998. The determining authority is Bridgend.…

Operational Β· Since 1998
Project stageOperating
  1. PlanningJul 1997 (completed)
  2. ConsentedSep 1997 (completed)
  3. Construction (completed)
  4. OperatingOct 1998 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2003-12-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.200 MW
Registered Capacity
1998
Commissioned

πŸ“‹ Project Overview

Tythegston Landfill Site is a 1.2 MW bioenergy / waste project in Wales. The applicant or operator on record is Renewable Power Generation Ltd. It is recorded as operational since October 1998. The determining authority is Bridgend.

πŸ”§ Technical Specifications

Capacity (MW)1.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperRenewable Power Generation Ltd
Owner / operatorRenewable Power Generation Ltd
Year consented1997
Commissioned / target1998
LocationTythegston Landfill Site Tythegston Mid Glamorgan, Mid Glamorgan
RegionWales
Coordinates51.4964274Β°N, 3.6565813Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1997-07-01
1997-09-04
1998-10-01