Tudworth Hall Farm Tudworth Field Road Hatfield, South Yorkshire, DN7 6HQ
Tudworth Field Road, Hatfield - Solar PV Panels is a 0.27 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is SJS Agriplant Limited. It is recorded as operational since January 2023. The determining authority is Doncaster, reference 22/00699/FUL.β¦
OperationalΒ· Since 2023
Project stageOperating
PlanningMar 2022 (completed)
ConsentedApr 2022 (completed)
ConstructionApr 2022 (completed)
OperatingJan 2023 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2022-04-27.
Registered planning capacity; not measured generation.
Tudworth Field Road, Hatfield - Solar PV Panels is a 0.27 MW solar farm project in Yorkshire and Humber. The applicant or operator on record is SJS Agriplant Limited. It is recorded as operational since January 2023. The determining authority is Doncaster, reference 22/00699/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.270 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
SJS Agriplant Limited
Owner / operator
SJS Agriplant Limited
Year consented
2022
Construction started
2022
Commissioned / target
2023
Location
Tudworth Hall Farm Tudworth Field Road Hatfield, South Yorkshire, DN7 6HQ