Trowbridge Sewage Treatment Works

Bradford Road, Trowbridge, Wiltshire, BA14 9AX

Trowbridge Sewage Treatment Works is a 1.2 MW bioenergy / waste project in South West. The applicant or operator on record is Wessex Water. It is recorded as operational since April 2016. The determining authority is Wiltshire, reference W/12/01818/WCM.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningSep 2012 (completed)
  2. ConsentedFeb 2013 (completed)
  3. ConstructionOct 2015 (completed)
  4. OperatingApr 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-05-16.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.200 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Trowbridge Sewage Treatment Works is a 1.2 MW bioenergy / waste project in South West. The applicant or operator on record is Wessex Water. It is recorded as operational since April 2016. The determining authority is Wiltshire, reference W/12/01818/WCM.

πŸ”§ Technical Specifications

Capacity (MW)1.200 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWessex Water
Owner / operatorWessex Water
Year consented2013
Construction started2015
Commissioned / target2016
LocationBradford Road, Trowbridge, Wiltshire, BA14 9AX
RegionSouth West
Coordinates51.3278698Β°N, 2.2181896Β°W

Additional published register fields

Registered technologySewage Sludge Digestion

πŸ“… Project Timeline

2012-09-28
2013-02-27
2015-10-19
2016-04-19