Battery Compound, Totnes Road, Ipplepen, Newton Abbot, Devon, TQ12 5TN
Totnes Road, Ipplepen - Micro Energy Storage Facility is a 0.2 MW battery storage project in South West. The applicant or operator on record is Aggregated Micro Power Holdings Plc. The planning application was refused. The determining authority is Teignbridge, reference 25/00815/β¦
Refused
Project stageRefused
PlanningMay 2025 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Planning Permission Refused.
Official register: July 2026
Recorded status: Planning Permission Refused. Source record updated 2025-07-25.
Registered planning capacity; not measured generation.
Totnes Road, Ipplepen - Micro Energy Storage Facility is a 0.2 MW battery storage project in South West. The applicant or operator on record is Aggregated Micro Power Holdings Plc. The planning application was refused. The determining authority is Teignbridge, reference 25/00815/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
0.200 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Aggregated Micro Power Holdings Plc
Owner / operator
Aggregated Micro Power Holdings Plc
Location
Battery Compound, Totnes Road, Ipplepen, Newton Abbot, Devon, TQ12 5TN