Torrington Avenue Battery Storage Facility is a 25 MW battery storage project in West Midlands. The applicant or operator on record is Power Initiatives Limited. The scheme is currently in the planning system, submitted May 2021. The determining authority is Coventry, reference F…

Revised
Project stageSuperseded by a new application
  1. PlanningMay 2021 (completed)
  2. Superseded by a new application (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2024-04-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

25.000 MW
Power Capacity

πŸ“‹ Project Overview

Torrington Avenue Battery Storage Facility is a 25 MW battery storage project in West Midlands. The applicant or operator on record is Power Initiatives Limited. The scheme is currently in the planning system, submitted May 2021. The determining authority is Coventry, reference FUL/2021/1299.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)25.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPower Initiatives Limited
Owner / operatorPower Initiatives Limited
LocationTorrington Avenue, Coventry, West Midlands, CV4 9GR
RegionWest Midlands
Coordinates52.3978732Β°N, 1.5718385Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (New REPD Ref)16279

πŸ“… Project Timeline

2021-05-21