Torr Leathann, Ardross - Battery Storage is a 5 MW battery storage project in Scotland. The applicant or operator on record is Energiekontor. The planning application was refused. The determining authority is Highland, reference 22/02442/FUL.…

Refused
Project stageRefused
  1. PlanningJun 2022 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2022-06-14.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Power Capacity

πŸ“‹ Project Overview

Torr Leathann, Ardross - Battery Storage is a 5 MW battery storage project in Scotland. The applicant or operator on record is Energiekontor. The planning application was refused. The determining authority is Highland, reference 22/02442/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW
Battery chemistryCo-located with RE

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperEnergiekontor
Owner / operatorEnergiekontor
LocationTorr Leathann Strathrory Ardross Alness, Highland, IV17 0YD
RegionScotland
Coordinates57.7689958Β°N, 4.2873788Β°W

Additional published register fields

Registered technologyBattery
Storage Co-location REPD Ref ID11450

πŸ“… Project Timeline

2022-06-06