Nightingale Park Barton Hill Way Torquay, Devon, TQ2 8JG
Torbay Hospital, Nightingale Park - Solar Panel Array is a 3.2 MW solar farm project in South West. The applicant or operator on record is TDA. Planning permission has been granted as of June 2022 and it is awaiting construction. The determining authority is Torbay, reference P/2β¦
Consented / Approved
Project stageConsented
PlanningNov 2021 (completed)
ConsentedJun 2022 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-03-04.
Registered planning capacity; not measured generation.
Torbay Hospital, Nightingale Park - Solar Panel Array is a 3.2 MW solar farm project in South West. The applicant or operator on record is TDA. Planning permission has been granted as of June 2022 and it is awaiting construction. The determining authority is Torbay, reference P/2021/1287.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
3.200 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
TDA
Owner / operator
TDA
Year consented
2022
Location
Nightingale Park Barton Hill Way Torquay, Devon, TQ2 8JG