Land North and West of Tonge Corner Farm, Tonge Corner Road, Tonge, Sittingbourne, Kent, Kent, ME9 9BB
Tonge Corner Farm is a 22 MW solar farm project in South East. The applicant or operator on record is Martifer Solar (Voltalia). It is recorded as operational since March 2016. The determining authority is Swale, reference SW/14/0224.β¦
OperationalΒ· Since 2016
Project stageOperating
PlanningMar 2014 (completed)
ConsentedAug 2015 (completed)
ConstructionJan 2016 (completed)
OperatingMar 2016 (current stage)
Closed (not yet reached)
Status in the official register: Operational.
Official register: July 2026
Recorded status: Operational. Source record updated 2016-08-24.
Registered planning capacity; not measured generation.
Tonge Corner Farm is a 22 MW solar farm project in South East. The applicant or operator on record is Martifer Solar (Voltalia). It is recorded as operational since March 2016. The determining authority is Swale, reference SW/14/0224.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
22.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Martifer Solar (Voltalia)
Owner / operator
Martifer Solar (Voltalia)
Year consented
2015
Construction started
2016
Commissioned / target
2016
Location
Land North and West of Tonge Corner Farm, Tonge Corner Road, Tonge, Sittingbourne, Kent, Kent, ME9 9BB