Battery Storage

Toddington Services, Hipsey Spinney - Battery Storage

S/O Toddington Services, W/O The M1 Motorway & E/O Hipsey Spinney, Dunstable, Bedfordshire, LU5 6HP

Toddington Services, Hipsey Spinney - Battery Storage is a 250 MW battery storage project in Eastern. The applicant or operator on record is Kona Energy Limited. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining authority is …

Consented / Approved
Project stageConsented
  1. PlanningFeb 2024 (completed)
  2. ConsentedJan 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-01-20.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

250.000 MW
Power Capacity

πŸ“‹ Project Overview

Toddington Services, Hipsey Spinney - Battery Storage is a 250 MW battery storage project in Eastern. The applicant or operator on record is Kona Energy Limited. Planning permission has been granted as of January 2025 and it is awaiting construction. The determining authority is Central Bedfordshire, reference CB/24/00414/FULL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)250.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKona Energy Limited
Owner / operatorKona Energy Limited
Year consented2025
LocationS/O Toddington Services, W/O The M1 Motorway & E/O Hipsey Spinney, Dunstable, Bedfordshire, LU5 6HP
RegionEastern
Coordinates51.9439392Β°N, 0.5010683Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (Old REPD Ref) 15573

πŸ“… Project Timeline

2024-02-15
2025-01-06