Solar Farm

Tir Nyth Soalr Park

Land To The South West (0.1 Km) Of Bryn Rhedyn And To The North (0.15 Km) Of Nant Y Fedw Farm Bedlinog, Mid Glamorgan, CF46 6UF

Tir Nyth Soalr Park is a 5 MW solar farm project in Wales. The applicant or operator on record is Global Renewable Construction. The planning application was refused. The determining authority is Merthyr Tydfil, reference P/15/0254.…

Refused
Project stageRefused
  1. PlanningJul 2015 (completed)
  2. Refused (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Refused.

Official register: July 2026

Recorded status: Planning Permission Refused. Source record updated 2016-05-04.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.000 MW
Registered Capacity

πŸ“‹ Project Overview

Tir Nyth Soalr Park is a 5 MW solar farm project in Wales. The applicant or operator on record is Global Renewable Construction. The planning application was refused. The determining authority is Merthyr Tydfil, reference P/15/0254.

Site Schematic

SUBSTATION ? ha Β· 5 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGlobal Renewable Construction
Owner / operatorGlobal Renewable Construction
LocationLand To The South West (0.1 Km) Of Bryn Rhedyn And To The North (0.15 Km) Of Nant Y Fedw Farm Bedlinog, Mid Glamorgan, CF46 6UF
RegionWales
Coordinates51.6975196Β°N, 3.3194456Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)90600

πŸ“… Project Timeline

2015-07-30