Thornholme Wind Farm is a 12 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Wind Prospect Developments. The planning application was refused. The determining authority is East Riding of Yorkshire, reference 11/03999/STPLFE.β¦
Refused
Project stageRefused
PlanningSep 2011 (completed)
Refused (project stopped here)
Consented (not reached)
Construction (not reached)
Operating (not reached)
Closed (not reached)
Status in the official register: Appeal Refused.
Official register: July 2026
Recorded status: Appeal Refused. Source record updated 2014-06-06.
Registered planning capacity; not measured generation.
Thornholme Wind Farm is a 12 MW onshore wind project in Yorkshire and Humber. The applicant or operator on record is Wind Prospect Developments. The planning application was refused. The determining authority is East Riding of Yorkshire, reference 11/03999/STPLFE.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
12.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Wind Prospect Developments
Owner / operator
Wind Prospect Developments
Location
Thornholme Fields, Rudston Road, Burton Agnes, East Riding Of Yorkshire, Humberside