πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

The Scrapyard, Bowbridge Lane - Battery Energy Storage System

The Scrapyard, Bowbridge Lane, Balderton, Newark, Nottinghamshire, NG24 3BZ

The Scrapyard, Bowbridge Lane - Battery Energy Storage System is a battery storage project in East Midlands. The applicant or operator on record is Conrad Energy (Developments) Limited. Planning permission has been granted as of August 2024 and it is awaiting construction. The de…

Consented / Approved
Project stageConsented
  1. PlanningDec 2023 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2024-09-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

The Scrapyard, Bowbridge Lane - Battery Energy Storage System is a battery storage project in East Midlands. The applicant or operator on record is Conrad Energy (Developments) Limited. Planning permission has been granted as of August 2024 and it is awaiting construction. The determining authority is Newark and Sherwood, reference 23/01913/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperConrad Energy (Developments) Limited
Owner / operatorConrad Energy (Developments) Limited
Year consented2024
LocationThe Scrapyard, Bowbridge Lane, Balderton, Newark, Nottinghamshire, NG24 3BZ
RegionEast Midlands
Coordinates53.0479564Β°N, 0.810699Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2023-12-01
2024-08-13