Onshore Wind

The Low Carbon Energy Generation Project at Keele University

Land Adj To Springpool Wood, Keele, Newcastle-Under-Lyme, Staffordshire, ST5 5BW

The Low Carbon Energy Generation Project at Keele University is a 1.9 MW onshore wind project in West Midlands. The applicant or operator on record is Keele University. It is recorded as operational since September 2021. The determining authority is Newcastle-under-Lyme, referenc…

Operational Β· Since 2021
Project stageOperating
  1. PlanningDec 2018 (completed)
  2. ConsentedMay 2019 (completed)
  3. ConstructionDec 2020 (completed)
  4. OperatingSep 2021 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2021-09-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

1.900 MW
Registered Capacity
2021
Commissioned

πŸ“‹ Project Overview

The Low Carbon Energy Generation Project at Keele University is a 1.9 MW onshore wind project in West Midlands. The applicant or operator on record is Keele University. It is recorded as operational since September 2021. The determining authority is Newcastle-under-Lyme, reference 18/00933/FUL.

Site Schematic

WEST MIDLANDS Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)1.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperKeele University
Owner / operatorKeele University
Year consented2019
Construction started2020
Commissioned / target2021
LocationLand Adj To Springpool Wood, Keele, Newcastle-Under-Lyme, Staffordshire, ST5 5BW
RegionWest Midlands
Coordinates53.0019102Β°N, 2.271024Β°W

Additional published register fields

Registered technologyWind Onshore
No. of Turbines2
Height of Turbines (m)77

πŸ“… Project Timeline

2018-12-20
2019-05-02
2020-12-02
2021-09-01