The Grange is a 8 MW solar farm project in South West. The applicant or operator on record is Elgin Energy EsCo. It is recorded as operational since March 2016. The determining authority is North Somerset, reference 14/P/1938/F.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningSep 2014 (completed)
  2. ConsentedFeb 2015 (completed)
  3. ConstructionDec 2015 (completed)
  4. OperatingMar 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2017-01-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

8.000 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

The Grange is a 8 MW solar farm project in South West. The applicant or operator on record is Elgin Energy EsCo. It is recorded as operational since March 2016. The determining authority is North Somerset, reference 14/P/1938/F.

Site Schematic

SUBSTATION ? ha Β· 8 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)8.000 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperElgin Energy EsCo
Owner / operatorElgin Energy EsCo
Year consented2015
Construction started2015
Commissioned / target2016
LocationThe Grange, Wick Lane, West Hewish, Banwell, Avon, BS24 6RR
RegionSouth West
Coordinates51.3720463Β°N, 2.8762821Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)186000

πŸ“… Project Timeline

2014-09-08
2015-02-03
2015-12-02
2016-03-30