Solar Farm

The Elms

The Elms Plough Lane Bishops Itchington Southam, Warwickshire, CV47 2QG

The Elms is a 10.4 MW solar farm project in West Midlands. The applicant or operator on record is Foresight Solar Fund. It is recorded as operational since March 2015. The determining authority is Stratford-on-Avon, reference 14/02341/FUL.…

Operational Β· Since 2015
Project stageOperating
  1. PlanningSep 2014 (completed)
  2. ConsentedNov 2014 (completed)
  3. ConstructionFeb 2015 (completed)
  4. OperatingMar 2015 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-07-31.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

10.400 MW
Registered Capacity
2015
Commissioned

πŸ“‹ Project Overview

The Elms is a 10.4 MW solar farm project in West Midlands. The applicant or operator on record is Foresight Solar Fund. It is recorded as operational since March 2015. The determining authority is Stratford-on-Avon, reference 14/02341/FUL.

Site Schematic

SUBSTATION ? ha Β· 10.4 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)10.400 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperForesight Solar Fund
Owner / operatorForesight Solar Fund
Year consented2014
Construction started2015
Commissioned / target2015
LocationThe Elms Plough Lane Bishops Itchington Southam, Warwickshire, CV47 2QG
RegionWest Midlands
Coordinates52.2141794Β°N, 1.4454952Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)294100

πŸ“… Project Timeline

2014-09-03
2014-11-27
2015-02-01
2015-03-31