Thames Way, Northfleet, Gravesend, Kent, DA11 8HN

Thames Way, Northfleet - Battery Energy Storage is a 100 MW battery storage project in South East. The applicant or operator on record is Speedgreen Limited. The scheme is currently in the planning system, submitted August 2025. The determining authority is Gravesham, reference 2…

In Planning
Project stageIn planning
  1. PlanningAug 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Application Submitted.

Official register: July 2026

Recorded status: Planning Application Submitted. Source record updated 2025-09-26.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

100.000 MW
Power Capacity

πŸ“‹ Project Overview

Thames Way, Northfleet - Battery Energy Storage is a 100 MW battery storage project in South East. The applicant or operator on record is Speedgreen Limited. The scheme is currently in the planning system, submitted August 2025. The determining authority is Gravesham, reference 20250730.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)100.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSpeedgreen Limited
Owner / operatorSpeedgreen Limited
LocationThames Way, Northfleet, Gravesend, Kent, DA11 8HN
RegionSouth East
Coordinates51.4365342Β°N, 0.3330552Β°E

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2025-08-14