Solar Farm

Tebworth - Solar Farm

East and W/O Tebworth Leighton Buzzard, Bedfordshire, LU7 9BP

Tebworth - Solar Farm is a solar farm project in Eastern. The applicant or operator on record is Sundon Green Limited. It is recorded as under construction since January 2024. The determining authority is Central Bedfordshire, reference CB/21/04219/FULL.…

Under Construction
Project stageUnder construction
  1. PlanningSep 2021 (completed)
  2. ConsentedMay 2022 (completed)
  3. ConstructionJan 2024 (current stage)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Under Construction.

Official register: July 2026

Recorded status: Under Construction. Source record updated 2026-03-06.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

πŸ“‹ Project Overview

Tebworth - Solar Farm is a solar farm project in Eastern. The applicant or operator on record is Sundon Green Limited. It is recorded as under construction since January 2024. The determining authority is Central Bedfordshire, reference CB/21/04219/FULL.

Site Schematic

SUBSTATION ? ha Β· MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperSundon Green Limited
Owner / operatorSundon Green Limited
Year consented2022
Construction started2024
LocationEast and W/O Tebworth Leighton Buzzard, Bedfordshire, LU7 9BP
RegionEastern
Coordinates51.9214552Β°N, 0.5774637Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Storage Co-location REPD Ref ID8895
Mounting Type for SolarGround
Solar Site Area (sqm)691100

πŸ“… Project Timeline

2021-09-20
2022-05-30
2024-01-01