Taunton Substation is a 49.9 MW battery storage project in South West. The applicant or operator on record is Pivot Power. The planning permission has expired. The determining authority is Somerset, reference 05/18/0040.…

Expired
Project stageConsent lapsed
  1. PlanningSep 2018 (completed)
  2. ConsentedSep 2018 (completed)
  3. Consent lapsed (project stopped here)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Planning Permission Expired.

Official register: July 2026

Recorded status: Planning Permission Expired. Source record updated 2020-09-17.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

49.900 MW
Power Capacity

πŸ“‹ Project Overview

Taunton Substation is a 49.9 MW battery storage project in South West. The applicant or operator on record is Pivot Power. The planning permission has expired. The determining authority is Somerset, reference 05/18/0040.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)49.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPivot Power
Owner / operatorPivot Power
Year consented2018
LocationTaunton Substation, Upcott Road, Bishops Hull, Taunton, Somerset, Somerset, TA4 1AF
RegionSouth West
Coordinates51.0180893Β°N, 3.1544274Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2018-09-13
2018-09-18