Tappaghan is a 19.5 MW onshore wind project in Northern Ireland. The applicant or operator on record is Greencoat UK Wind. It is recorded as operational since February 2005. The determining authority is Fermanagh and Omagh, reference L/2002/1042/F.…

Operational Β· Since 2005
Project stageOperating
  1. PlanningAug 2002 (completed)
  2. ConsentedNov 2003 (completed)
  3. Construction (completed)
  4. OperatingFeb 2005 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2015-01-05.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

19.500 MW
Registered Capacity
2005
Commissioned

πŸ“‹ Project Overview

Tappaghan is a 19.5 MW onshore wind project in Northern Ireland. The applicant or operator on record is Greencoat UK Wind. It is recorded as operational since February 2005. The determining authority is Fermanagh and Omagh, reference L/2002/1042/F.

Site Schematic

NORTHERN IRELAND Β· ? turbines Β· ? kmΒ²

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)19.500 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGreencoat UK Wind
Owner / operatorGreencoat UK Wind
Year consented2003
Commissioned / target2005
LocationLack, Tappaghan Mountains, Northern Ireland, Co. Fermanagh
RegionNorthern Ireland
Coordinates54.5471356Β°N, 7.6955798Β°W

Additional published register fields

Registered technologyWind Onshore
Turbine Capacity (MW)1.5
No. of Turbines13

πŸ“… Project Timeline

2002-08-01
2003-11-03