Taplins Farm solar park is a 5.9 MW solar farm project in South East. The applicant or operator on record is PS Renewables. It is recorded as operational since June 2016. The determining authority is Hart, reference 14/00998/MAJOR.…

Operational Β· Since 2016
Project stageOperating
  1. PlanningMay 2014 (completed)
  2. ConsentedOct 2014 (completed)
  3. ConstructionMay 2016 (completed)
  4. OperatingJun 2016 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2016-07-01.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.900 MW
Registered Capacity
2016
Commissioned

πŸ“‹ Project Overview

Taplins Farm solar park is a 5.9 MW solar farm project in South East. The applicant or operator on record is PS Renewables. It is recorded as operational since June 2016. The determining authority is Hart, reference 14/00998/MAJOR.

Site Schematic

SUBSTATION ? ha Β· 5.9 MW Β· ? panels

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)5.900 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPS Renewables
Owner / operatorPS Renewables
Year consented2014
Construction started2016
Commissioned / target2016
LocationLand East Of Taplins Farm Lane Winchfield Hook Hampshire, Hampshire
RegionSouth East
Coordinates51.2884587Β°N, 0.8835047Β°W

Additional published register fields

Registered technologySolar Photovoltaics
Mounting Type for SolarGround
Solar Site Area (sqm)134000

πŸ“… Project Timeline

2014-05-30
2014-10-20
2016-05-01
2016-06-15