Battery Storage

Tanners Lane - Battery Energy Storage System

Off Tanners Lane, Coventry, West Midlands, CV7 7DD

Tanners Lane - Battery Energy Storage System is a 30 MW battery storage project in West Midlands. The applicant or operator on record is Tag Energy Development UK Limited. The scheme is currently in the planning system, submitted October 2023. The determining authority is Solihul…

Revised
Project stageSuperseded by a new application
  1. PlanningOct 2023 (completed)
  2. Superseded by a new application (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Status in the official register: Revised.

Official register: July 2026

Recorded status: Revised. Source record updated 2024-03-12.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

30.000 MW
Power Capacity

πŸ“‹ Project Overview

Tanners Lane - Battery Energy Storage System is a 30 MW battery storage project in West Midlands. The applicant or operator on record is Tag Energy Development UK Limited. The scheme is currently in the planning system, submitted October 2023. The determining authority is Solihull, reference PL/2023/02051/PPFL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)30.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperTag Energy Development UK Limited
Owner / operatorTag Energy Development UK Limited
LocationOff Tanners Lane, Coventry, West Midlands, CV7 7DD
RegionWest Midlands
Coordinates52.402358Β°N, 1.6050868Β°W

Additional published register fields

Registered technologyBattery
Are they re-applying (New REPD Ref)17526

πŸ“… Project Timeline

2023-10-02