πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Battery Storage

Tanners Lane - Battery Energy Storage Facility (Phase One)

Newlands Farm Tanners Lane Fareham, Hampshire, PO14 1BL

Tanners Lane - Battery Energy Storage Facility (Phase One) is a 40 MW battery storage project in South East. The applicant or operator on record is British Solar Renewables. Planning permission has been granted as of November 2019 and it is awaiting construction. The determining…

Consented / Approved
Project stageConsented
  1. PlanningSep 2019 (completed)
  2. ConsentedNov 2019 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2022-04-07.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

40.000 MW
Power Capacity

πŸ“‹ Project Overview

Tanners Lane - Battery Energy Storage Facility (Phase One) is a 40 MW battery storage project in South East. The applicant or operator on record is British Solar Renewables. Planning permission has been granted as of November 2019 and it is awaiting construction. The determining authority is Fareham, reference P/19/1019/FP.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)40.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperBritish Solar Renewables
Owner / operatorBritish Solar Renewables
Year consented2019
LocationNewlands Farm Tanners Lane Fareham, Hampshire, PO14 1BL
RegionSouth East
Coordinates50.8320891Β°N, 1.1896013Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2019-09-02
2019-11-26