Tangy, Kilkenzie, Campbeltown, Argyll And Bute, Argyll and Bute, PA28 6QD
Tangy 4 Wind Farm is a 80 MW onshore wind project in Scotland. The applicant or operator on record is Scottish & Southern (SSE). Planning permission has been granted as of December 2019 and it is awaiting construction. The determining authority is Scottish Government (S36), referβ¦
Consented / Approved
Project stageConsented
PlanningSep 2018 (completed)
ConsentedDec 2019 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-08-11.
Registered planning capacity; not measured generation.
Tangy 4 Wind Farm is a 80 MW onshore wind project in Scotland. The applicant or operator on record is Scottish & Southern (SSE). Planning permission has been granted as of December 2019 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00000673.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
80.000 MW
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
Scottish & Southern (SSE)
Owner / operator
Scottish & Southern (SSE)
Year consented
2019
Location