πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content
Bioenergy / Waste

Sutton Courtenay Landfill Scheme

Appleford Sidings, Abingdon, Oxfordshire, Oxfordshire

Sutton Courtenay Landfill Scheme is a 5.6 MW bioenergy / waste project in South East. The applicant or operator on record is Waste Recycling Group. It is recorded as operational since March 1999. The determining authority is Vale of White Horse.…

Operational Β· Since 1999
Project stageOperating
  1. PlanningDec 1997 (completed)
  2. ConsentedMay 1998 (completed)
  3. Construction (completed)
  4. OperatingMar 1999 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2005-06-30.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

5.600 MW
Registered Capacity
1999
Commissioned

πŸ“‹ Project Overview

Sutton Courtenay Landfill Scheme is a 5.6 MW bioenergy / waste project in South East. The applicant or operator on record is Waste Recycling Group. It is recorded as operational since March 1999. The determining authority is Vale of White Horse.

πŸ”§ Technical Specifications

Capacity (MW)5.600 MW

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperWaste Recycling Group
Owner / operatorWaste Recycling Group
Year consented1998
Commissioned / target1999
LocationAppleford Sidings, Abingdon, Oxfordshire, Oxfordshire
RegionSouth East
Coordinates51.6317257Β°N, 1.2674419Β°W

Additional published register fields

Registered technologyLandfill Gas

πŸ“… Project Timeline

1997-12-18
1998-05-18
1999-03-05