Land To South Of A228, Sundridge Hill, Cuxton, Rochester,, Kent, ME2 1LB
Sundridge Hill is a 49.5 MW battery storage project in South East. The applicant or operator on record is RNA Energy. It is recorded as under construction since February 2022. The determining authority is Medway, reference MC/17/3770.β¦
Under Construction
Project stageUnder construction
PlanningNov 2017 (completed)
ConsentedAug 2018 (completed)
ConstructionFeb 2022 (current stage)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Under Construction.
Official register: July 2026
Recorded status: Under Construction. Source record updated 2022-03-17.
Registered planning capacity; not measured generation.
Sundridge Hill is a 49.5 MW battery storage project in South East. The applicant or operator on record is RNA Energy. It is recorded as under construction since February 2022. The determining authority is Medway, reference MC/17/3770.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Capacity (MW)
49.500 MW
Battery chemistry
Stand-alone Storage
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
RNA Energy
Owner / operator
RNA Energy
Year consented
2018
Construction started
2022
Location
Land To South Of A228, Sundridge Hill, Cuxton, Rochester,, Kent, ME2 1LB