Stracathro - Battery Energy Storage System is a 249 MW battery storage project in Scotland. The applicant or operator on record is Opdenergy UK 8 Limited. Planning permission has been granted as of August 2025 and it is awaiting construction. The determining authority is Scottish…

Consented / Approved
Project stageConsented
  1. PlanningJan 2025 (completed)
  2. ConsentedAug 2025 (current stage)
  3. Construction (not yet reached)
  4. Operating (not yet reached)
  5. Closed (not yet reached)

Status in the official register: Planning Permission Granted.

Official register: July 2026

Recorded status: Planning Permission Granted. Source record updated 2025-09-11.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

249.000 MW
Power Capacity

πŸ“‹ Project Overview

Stracathro - Battery Energy Storage System is a 249 MW battery storage project in Scotland. The applicant or operator on record is Opdenergy UK 8 Limited. Planning permission has been granted as of August 2025 and it is awaiting construction. The determining authority is Scottish Government (S36), reference ECU00004807.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)249.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperOpdenergy UK 8 Limited
Owner / operatorOpdenergy UK 8 Limited
Year consented2025
LocationAdj Addicate Wood and Huntly Wood & 1.6 km S/O Stracathro Services, Brechin, Angus, DD9 7PU
RegionScotland
Coordinates56.7615345Β°N, 2.6141395Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2025-01-09
2025-08-13