Battery Storage

Stony Energy Storage Facility

Land to the south west of Stony Stratford Substation, south of Stratford Road, Milton Keynes, Buckinghamshire, MK19 6DZ

Stony Energy Storage Facility is a 79.9 MW battery storage project in South East. The applicant or operator on record is Gore Street Energy Storage Fund. It is recorded as operational since July 2023. The determining authority is Buckinghamshire, reference 17/02259/APP.…

Operational Β· Since 2023
Project stageOperating
  1. PlanningJul 2017 (completed)
  2. ConsentedSep 2021 (completed)
  3. ConstructionJul 2022 (completed)
  4. OperatingJul 2023 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2024-05-28.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

79.900 MW
Power Capacity
2023
Commissioned

πŸ“‹ Project Overview

Stony Energy Storage Facility is a 79.9 MW battery storage project in South East. The applicant or operator on record is Gore Street Energy Storage Fund. It is recorded as operational since July 2023. The determining authority is Buckinghamshire, reference 17/02259/APP.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)79.900 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperGore Street Energy Storage Fund
Owner / operatorGore Street Energy Storage Fund
Year consented2021
Construction started2022
Commissioned / target2023
LocationLand to the south west of Stony Stratford Substation, south of Stratford Road, Milton Keynes, Buckinghamshire, MK19 6DZ
RegionSouth East
Coordinates52.0181928Β°N, 0.8685656Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2017-07-14
2021-09-03
2022-07-01
2023-07-31