Stoneshollow Solar Farm is a battery storage project in East Midlands. The applicant or operator on record is JBM Solar Projects Limited. Planning permission has been granted as of August 2022 and it is awaiting construction. The determining authority is Hinckley and Bosworth, reβ¦
Consented / Approved
Project stageConsented
PlanningNov 2021 (completed)
ConsentedAug 2022 (current stage)
Construction (not yet reached)
Operating (not yet reached)
Closed (not yet reached)
Status in the official register: Planning Permission Granted.
Official register: July 2026
Recorded status: Planning Permission Granted. Source record updated 2025-02-03.
Registered planning capacity; not measured generation.
Stoneshollow Solar Farm is a battery storage project in East Midlands. The applicant or operator on record is JBM Solar Projects Limited. Planning permission has been granted as of August 2022 and it is awaiting construction. The determining authority is Hinckley and Bosworth, reference 21/01395/FUL.
Site Schematic
Schematic diagram β not to scale. Illustrative layout based on project specifications.
π§ Technical Specifications
Battery chemistry
Co-located with RE
π Grid Connection & Infrastructure
π’ Development & Ownership
Developer
JBM Solar Projects Limited
Owner / operator
JBM Solar Projects Limited
Year consented
2022