Land Adjacent To Electricity S, Stonehill, Charlton, Malmesbury,, Wiltshire, SN16 9RP

Stonehill Energy Storage / Upper Minety is a 50 MW battery storage project in South West. The applicant or operator on record is Penso Power (BW ESS). It is recorded as operational since December 2020. The determining authority is Wiltshire, reference 17/05526/FUL.…

Operational Β· Since 2020
Project stageOperating
  1. PlanningJun 2017 (completed)
  2. ConsentedSep 2017 (completed)
  3. ConstructionDec 2019 (completed)
  4. OperatingDec 2020 (current stage)
  5. Closed (not yet reached)

Status in the official register: Operational.

Official register: July 2026

Recorded status: Operational. Source record updated 2026-03-09.

Registered planning capacity; not measured generation.

DESNZ source publication Β· Search the full register Β· Definitions and coverage

50.000 MW
Power Capacity
2020
Commissioned

πŸ“‹ Project Overview

Stonehill Energy Storage / Upper Minety is a 50 MW battery storage project in South West. The applicant or operator on record is Penso Power (BW ESS). It is recorded as operational since December 2020. The determining authority is Wiltshire, reference 17/05526/FUL.

Site Schematic

GRID CONNECTION TRANSFORMER 33 kV DC BUSBAR 1234567891011121314151617181920 ? Γ— Battery Units

Schematic diagram β€” not to scale. Illustrative layout based on project specifications.

πŸ”§ Technical Specifications

Capacity (MW)50.000 MW
Battery chemistryStand-alone Storage

πŸ”Œ Grid Connection & Infrastructure

🏒 Development & Ownership

DeveloperPenso Power (BW ESS)
Owner / operatorPenso Power (BW ESS)
Year consented2017
Construction started2019
Commissioned / target2020
LocationLand Adjacent To Electricity S, Stonehill, Charlton, Malmesbury,, Wiltshire, SN16 9RP
RegionSouth West
Coordinates51.6053358Β°N, 2.0040094Β°W

Additional published register fields

Registered technologyBattery

πŸ“… Project Timeline

2017-06-29
2017-09-21
2019-12-01
2020-12-01